Dear planner



A hammock in P3 is kind of act like a summary bar



With that intension, you dont want to assign any lag to the relationship between the hammock and the associated activity. (Because it will then reflected a wrong summary)



In order to have the hammock show the earliest start date of a series of activities you need to link them as SS with the Hammock activity. Same applied to Finish date.



Cheers



Alex

P
Philip Rawlings 👤 Member for 21 years 6 months

Hi

Just one other thing to be aware of.

P3 specifies that the predecessor(s) to a hammock must be SS and the successor(s) must be FF. BUT it allows you to enter any relationship type (e.g. SF, with lags) but these relations are just ignored. Daft, but there it is!

D
Drew Palmer 👤 Member for 25 years 4 months

Alexandre,



If your hammock has no predecessors P3 will assume that the hammock starts on the data date - regardless of any actual data you may enter.



If you already have a predecessor, make sure that you have input an actual start date on this activity. If there is no predecessor I suggest creating a milestone to signify the start of the project (start of PM activity) and designating this milestone as the predecessor of your PM hammock - enter your actual start against this milestone and you should be in business.



Cheers,

Drew

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts