EARNED VALUE

J
Jonathan Kirby 👤 Member for 21 years 4 months

Louise

You need to get the Estimate/contract price make up for the project and work out the ’value’ of all the activities in your programme. You then can put the value onto each activity. this is easier said than done with many projects as the conntract price breakdown rarely transtates simply into the programme activities. It also requires a sufficiently detailed programme so the value spread on the activity is meaningful.

Once done and early/late date baselines set up, as you progress activities the corresponding Value becomes ’earned’. you can then produce graphs etc of the earned value to as the project progresses, graphs for various selections of activities can also be produced.

This is useful to then compare the earned value against actual costs on the project and monitor your cost to earned value ratio. eg high earned value and low actual cost is good. You can then also make forecasts and projections on the likely end cost.

hope this helps.

JK

S
Steven Oliver 👤 Member for 23 years 7 months

Earned Value = Budget Cost of Work Performed (BCWP) and has a very well defined value equivalent to Percent Complete * Budget. At any point in time you should know the budget for an activity, so the hard part is defining % complete.



See Paul Harris’s website for some very good info and application of Ev.





HTH




Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts