Original Duration vs Remaining Duration

K
Kari Lucas 👤 Member for 15 years 11 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Kari,

It is a setting in P6. Project Window-> Calculation tab-> Activities. Tick Link Budget and At Completion for not started Activities and select Reset Remaining Duration and Units to Original if you wanted to synchronize OD and RD. Select Reset Original Duration and Unit to Remaining if you want to maintain remaining duration when progress actual has been remove to activity.