Shahzad Munawar 👤 Member for 22 years 11 months

Data date will cover the purpose of Run date as you want to show in Legend in Printing

R
Ronald Winter 👤 Member for 23 years 5 months

There is no need to go to all of that trouble. The footer is fully customizeable. Just go to File / Page Setup / Footer. The Help file can help you for there. Good luck!

N
Nourjamal Izbasarova 👤 Member for 22 years 2 months

Hello Daya,

Probably this is not the best solution, but still you can try: i saved the schedule as a PDF file, and then deleted the time (Adobe Acrobat 5.0 has a ’touch up text tool’, which allows to make changes to the text)

hope it helps,

NJ

R
Raj Maurya 👤 Member for 21 years 10 months

Dear Daya,

You can use the data date instead of run date. I know this not the true solution of your question but you can run the schedule on current date and then use data date.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts