It all depends upon what type of custom data field you are trying to update. Here is a quick reference chart,
Type Description
C Character
N Numeric (with no decimal places)
P Precision (numeric with up to two decimal places)
SF Start DateFinish Date
Length: The length of the field depends on the type of data selected.
Type Description Length
C Character 1-20
N Numeric 1-10
P Precision Numeric 4-11 (includes decimal point)
SF Start DateFinish Date The length for Start and Finish dates depends on the projects planning unit and the selected date format. P3 automatically sets the lengths for date data items.
Good luck!