So far i have been utilizing weightage based on cost and the report that i print is from the report writer.
Thanks. I will qualify for manhours as well as cost to arrive at weightage. Does P3 print weightage reports.
I am also interested in understanding how to assign weightage based on manhrs. Can any one help me out?
Pls. qualify, how do you intend to use the weightages? If you have already one homogenous resource (i mean uniform unit of measure, say cost of each activity) inputted in your schedule, you don’t need "to give" weightages to the activities to roll up the progress at different levels.
proj_planner