Target Plan

Z
Zq qz 👤 Member for 23 years

Agree with Dayan last post, but for schedule with sub project. Check this.Go to

TOOLS>>>>SCHEDULE>>>>OPTIONS>>>>>ADVANCE>>>>go to TICK PROJECT GROUP SCHEDULING & PROJECT GROUP....

HOPE everything is ok




M
MK TSE 👤 Member for 24 years 3 months

Christian, have you tried the function on P3: Tools -> Project Utilities -> Targets -> select the target -> press Update button.

Target 2 will be updated by the value on CURR.

(Before you try, make copy first, just in case)

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

As a suggestion pls check your layout of TARGET 2 file................ may be some activities might have been hidden due to filter set up or organization set up....................and run schedule after progress update option, try to navigate the links between activities which is not giving 100% eventhough the activity is scheduled to be completed with reference to the data date, may be some activities might not have been closed well within the data date during previous progress updates due to some reasons like layout setup etc.............



Check for the option choosen in the update progress under

estimate progress within updateperiod for:

option 1. All activities

2. Selected activities



Click option 1 to be checked properly, Also note that some activities completion date if fall exactly on the data date will not show 100%



i hope that the above will solve your problem.............

L
Luca Basile 👤 Member for 22 years 11 months

You could update one, and export the progress information in the other.


C
Christian Adrian De Vera 👤 Member for 23 years

Thanks Maria but it is only under one project and the data date for the CURR vs. ASPL are the same.. I still cant figure how can this be possible & how can I resolve this in a faster way because updating the ASPL manually and checking the CURR takes to much time...



regards,



Christian

M
Maria Ahlberg 👤 Member for 22 years 1 month

It may be a bigger problem, but check if you have the same data date in all sub-projects. I run across the result you describe when one sub-project had slipped in updating and we had 2 different data dates in the same main project (for you Target 2) Different data dates can give strange results.

/Maria

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts