Updatingn the schedule in P-3

A
Ali Kashif 👤 Member for 17 years 8 months
T
Tommy Nug 👤 Member for 18 years 6 months

For hammock activities, You have to update actual start date and actual finish date. The percentage of hammock activities shall be automatically calculated.



Cheers,

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Ernani,



To create a Hammock Activity, create a new activity in their specific level and change the activity type to "hammock" then tie up with the predecessor (SS) & successor (FF).



HTH.



Arnold


E
Ernani Garena 👤 Member for 17 years 6 months

Hello! Can anybody teach me how to create hammock activities. A sample schedule will be of great help for me to understand more hammock activities.



You can email me thru [email protected]



Thank you very much!

A
Azeem Abdul 👤 Member for 17 years 6 months

Hammock is used when in an activity start and end dates are known and we want it (activity) to pick duration and adjust itself within the limits (start and end dates).



You can find hammock activities used in Cranes and Hoists section of our programme.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts