I suggest that you copy the P6 Global Calendar and turn the copy into a Project Calendar. Then using Global Change, change all of the activity calendars from the original to the Project Calendar. Now you can change the hours in the Project Calendar as needed. Good luck!
Sorry I need to know how to restrict hours on a contract without changing the global calendars in P6