how to unstatus a project in P3
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Absolutely, but with a minor change....
There should be a space between the quotes to run this Global Change. Else it keeps giving you Invalid Data error.
Regards
Richard
It goes something like this
AS EQ ""
AF EQ ""
PCT EQ 0
OD EQ RD
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au