Hello Dan,



What you describe looks like a Hammock activity:



To behave as expected, the activity should have a ’Hammock’ Activity Type, and should be linked to one predecessor with a Start to Start relationship, and to one successor with a Finish to Finish relationship (meaning that in your case the successor should be a Finish Milestone).



Hope this helps



Jean-Philippe