Inaccurate Total Float Calcs
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Beth,
the P3 "mpx-to-P3" engine does not fully understand the data that MS Project has sent to its mpx file
almost every time you will import into P3 a MPP file you will have such errors
Paul Harris recommends to export the MSP file to an Excel worksheet or a dBase file then to import this file into P3.
Alexandre
No constraints..already checked that. Since it is picking up the project overview will finish date, I am with Dieter that is some issue between MPP and P3. New projects I entered myself I have no issues only the ones I imported from Project. Thanks for the help. Beth
The most probable answer of odd floats in the programme is CONSTRAINTS. Check if you have hard constraints assigned to those activities.
Dieter,
Thanks for your reply. I do not have access to P6. I have noticed that my new projects are fine so it must something I cannot affect. Thanks again.
Beth
Beth
Some time ago we had a similar situation and couldnt solve it the direct way. But when we imported MSP into P6, then exported into P3 it was ok. Honestly, I dont know why.
Regards
Dieter
please go to other threads (i dont know the link), "favorite feature in P3e/P6"