Forum Guest 👤 Member for 17 years 4 months
M
MK TSE 👤 Member for 24 years 3 months

To overcome create the spreadsheet, I usually create 2 dummy activities in P3, then export them in DBF format with selected fields.

Open DBF in Excel, do my edit and save it in DBF.

Then import.

L
Luca Basile 👤 Member for 22 years 11 months

Pay attention to save the file in DBIII format and not DBIV, otherwise P3 will not be able to read it.



Before to run the import You must have close the file in excel or again P3 will be not able to read it.

L
Luca Basile 👤 Member for 22 years 11 months

In Your excel file for each column insert these heading:

ACT Fill with Activity ID

TITLE Fill with Activity title (if You need)

OD Fill with Original duration



Example

ACT TITLE OD

A1000 Cut & fill 10

A1010 Stabiliz 8

Etc …



Then in excel select all the area and from the menu select “Insert->Name->Define” and give a name. You are making a database

Save the file in DBIII format



In P3 “Tools->Project Utilities->Import” write down the path, to Your file example “C:Projfile.dbf” and run it

S
Shahzad Munawar 👤 Member for 22 years 11 months

This topic was discussed hundred times. So find this in reserch:



Transfer data from Excel to P3

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts