Forecasting % Complete Using P6

B
Bob Foden 👤 Member for 18 years 8 months
S
Sajid Balma 👤 Member for 19 years

Tools>Update Progress; choose your date & apply

In schedule % complete you will get the total % as if everything going exactly the way they were planned (forecast%)