P3.1 Planned Percentage

P
Paul Harris 👤 Member for 25 years 2 months

I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au




P
Paul Harris 👤 Member for 25 years 2 months

I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au




Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts