Thanks Paul, that’ll do for me. Easy when you know how ... :)
I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.