Independent activity

P
Paul Harris 👤 Member for 25 years 2 months

By default activities are "Independent" in MSP. That is when a resource is assigned to an activity then it will acknowledge the resource calendar, unless one checks the "Do not acknowledge resource calendar box". MSP does not have a equivalent to a Meeting task so they are often correctly imported as Independent. But as there are so many ways of importing a MSP schedule into P3 I am not sure they all treat the tasks the same way.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au