Thanks Paul for the explanation.
Regards,
Moutaz
By default activities are "Independent" in MSP. That is when a resource is assigned to an activity then it will acknowledge the resource calendar, unless one checks the "Do not acknowledge resource calendar box". MSP does not have a equivalent to a Meeting task so they are often correctly imported as Independent. But as there are so many ways of importing a MSP schedule into P3 I am not sure they all treat the tasks the same way.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au