Dear Arnol,
I found out the problem, another activity has got the latest date, not the project completion date.
Thanks a lot,
Moutaz
Hello Moutaz,
Try to check your "Project must finish by", in File --> Project Overview. You can remove or change it to the Finish Date of your Project.
Regards,
Arnold