Reviewing a schedule

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

In addition to Ron Winter’s guidelines,



It is also preferable to look at the contract regarding specification for planning and scheduling.



In one of the project I was involved, there was a general specification on planning and scheduling, so in my review, i just flag what was not included as per the specification.



The review of CPM is very important to look at the lofig in arriving at the CPM, it is really reasonable, no manipulation of logic, etc., etc.



Regards,

Charlie

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Ron Winter indeed it is brilliant.



Do you have anything regarding reviewing a schedule during progress update



reviewing a schedule for revise baseline.



We do need some sort of a guidance for the above.



Regards,



Charlie

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts