im talking of "weighting factor", if you had used "costs" you must update your program with costs, and not with any other options.
Yes Anoon, there is three ways on how to update the program duration,resources and cost. these three i used cost. even my friend hes a planner too, he cant resolve this problem. you can try it to your program, just let me know if something remedy.
thanks
have you chosen "costs" as your weighting factor before running your schedule? how do you update your schedule?