Retainage in P3

Z
Zubair Usmani 👤 Member for 21 years

Dont show the cost complete 100%. Make the cost% idependent to progress duration% in auto cost rule of P3.

you can even show the activity as completed but cost part you can claim later when you want.

M
Marc Borburgh 👤 Member for 22 years 1 month

what you could do is taking off a percentage of the cost on each activity and put the remainder on a milestone until the terms are in accordance with the terms of the construction contract.



Once everything is correct with the contract, you can "release" the milestone and mark it 100%.



withholding a certain percentage of progress on the activities will cause out-of-sequence progressing and might "mess up" your schedule.