Actual resources consumed

P
PINAN T. 👤 Member for 18 years 10 months

you can record actuals in resource window, and store period performance



but im not sure if p3 reports can generate actual quantities graph and loading, only current and planned will be shown as far as i know



do it in excel

S
Salahuddin Ahmed 👤 Member for 18 years 2 months

Pinan,



Thanks for your reply.



Still my question is how do i enter data in P3 and generate tabular and graphical report.



Pipe fitter Mon - Fri 5*8= 40

Millwright Mon - Fri 5*8= 40



I am recoding progress every week and the reports to be submitted every Monday.



Appreciate help.



Salah

P
PINAN T. 👤 Member for 18 years 10 months

get it from daily TIMESHEETS from ur Timekeeper..



Use Excel Charts for Comparison

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts