what’s the best way for updating and save Schedules?

S
Shazia khan 👤 Member for 18 years 1 month

Hadi.



Ask your client / consultant how often they wants Schedule



update.



in General SChedule update bi weekly. cut of date last working days...for example Mon to Sat...sunday is off



2nd update Monthly....cut off date depands upon your projects requirment....



in general 24th or 25th date ...cut off date...