Longest path has a chequered reputation in P3.1, I don’t have much experience with it but understand that it doesn’t exactly work as advertised.
I use TF=0.
Actually, if you have several "near critical" paths you can go to Tools/options/critical activities and set this to a larger number, I plan in hours and usually set critical activities to be TF<10 hours for critical paths and TF<50 hours to highlight near critical mass work.