DATA DATE FOR P3

C
charan hari 👤 Member for 18 years 7 months
D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Charan

The data date is the start of the planning period - i.e. a part of it. If you’ll report until Feb 29, the data date will be March 1st.

Regards

Dieter

M
Muhammad Zeeshan Khan 👤 Member for 18 years 3 months

cheery what you actually presents in the data like what thing you are emphasize on you presentation i appreciate if some one reply as i am very novice planner



thanks in advanced for all your replies


C
charan hari 👤 Member for 18 years 7 months

Thanks for reply.But I am using planning units as hours not days.



As I am using planning units as hours then I used data date as closing of the business day i,e 29th Feb 17.00 Hours.

T
Taqi Hasan 👤 Member for 23 years 4 months

If you want to show progress till 29th Feb. data date should be the next day, i.e. 01 March, otherwise progress on Feb 29 won’t be considered by P3. P3 calculates progress at the beginning of the data date and not at the end (assuming ’day’ as the planning unit.)

C
charan hari 👤 Member for 18 years 7 months

Hi James,



Thanks for reply.I have progress till 29th Feb then I used same date & time as data date.



Cheers,

Cherry

J
James Barnes 👤 Member for 18 years 9 months

I suspect, for monthly progress, that it’s more a matter of presentation than accuracy whether you set the data date as the evening of the last day or the morning of the first day of the month.



As a general rule, the data date should be the date that the progress data you are entering is valid for. If you are producing an end of month report then you probably have collected the data a week beforehand. Thus your data date should be something like the 22nd Feb or you need to add an estimate of one week’s progress to the progress data you have in hand.



If the progress data you have in hand is correct up to 5pm on 29th Feb, then yes, that should be your data date. This is what I would set it as, unless specifically told otherwise.



Do you have a plan which is scheduled in hours but is only being reoprted once a month?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts