hi can we say schdule of Pert .....any one have tips and useful link on p3 please forward me on [email protected]
also by level
level 1 schedule
level 2 schedule
;
;
;
;
;
1. Barchart
2. CPM
3. Linear
4. Line of Ballance
5. Milestone
6. Completion
7. Recovery
8. 90-Day (Start-up)
come to mind immediately, although I am sure that there are others. Perhaps he was thinking about the "Levels of Schedules?"
My recommendation is that before you go into your next interview, that you grab a good book on Construction Scheduling and read it from cover to cover. The subject is simply fascinating and very diverse!
1. Presentation Schedule - for presentation only (maybe level 1)
2. Internal Schedule - the one you discuss (quarrel) with your boss
3. Commercial Schedule - the one providing your bread and butter (be careful with this one)
just guessing!