Unable to Split activity

M
Mangesh Khuspe 👤 Member for 19 years 2 months

Hi

Dieter, thanks for ur support and reply, yeah that activity had not started, the problem is solved.

Cheers



Mangesh

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Mangesh

I assume this activity wasn’t started. Only activities in progress you can suspend and resume.

Was this the answer to your question?

Regards

Dieter

A
A D 👤 Member for 19 years

Mangesh FYI,



In P3, if u r splitting activity, then UPT is constant for all timeperiods.



Is ur UPT constant?



Cheers,



Rav

M
Mangesh Khuspe 👤 Member for 19 years 2 months

Hi

willem,

actually i want to do resource levelling of my project and for that i want to split some activities, but when i schedule, the p3 does not split activities.

wht may be the possible reason.



Cheers



Mangesh

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts