I thought I understood Total Floats
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Thanks,
It was the calendars.
All fixed now!
Cheers!
Hi Brian
TF of an activity depends on the assigned calendar.
- Your activities have a calendar with 7 working days a week
- The Milestone has a calendar with 5 working days a week + a public holiday between MS and the project’s end. E.g.:
LTC Start Sep. 12 with OD=9d--> End Sep 20
Dirt Start Sep. 21 with OD=7d--> End Sep 27
Project’s end: Nov 14 with a public holiday (Oct 3, German national day) --> TF = 48days for LTC&Dirt and 33days for the MS.
OK?
Regards
Dieter
Hi Brian,
Its not always linear!!
Check the pred. of both activities (LTC. & Dirt Excavation) and youll get for sure one with 33 days of total float...
Regards
JK