Ferdinand U. 👤 Member for 18 years 10 months

Report the Status of Milestones and its variance with the actual dates and effects to the schedule, like delayed analysis reports

F
Ferdinand U. 👤 Member for 18 years 10 months

Try the Filtered Layer Reports-- MOst Delayed Activities with floats, No. of Activity Started, No. of Activity Completed, No. of Activity in progress

I
Imran Malik 👤 Member for 22 years

Believe me it is not easy here in dubai to ask contractors for quantities or client for cost. I am well aware of EVMS and used them previously. But now I am looking for something else base on information I have is only duration and milestones.

I
Ian Mackrell 👤 Member for 18 years 4 months

Imran,



An accurate tool for measuring any number of project is Earned Value Management.



A project team should be able to give you SPI and CPI values without disclosing any confidential information i.e. commercial.



However, to produce one report for all projects, you will need BCWP (BQWP), ACWP (AQWP) and BCWS (BQWS) from all projects. These figures are not too much for ask for for some!

I
Imran Malik 👤 Member for 22 years

Dear. Thanks for your response but i mentioned earlier that i dont have manhours or cost for the activities. Someone told me a method to use float and count of the activities but i am not sure how?

I
Imran Arshad 👤 Member for 18 years 7 months

Dear Imran,

You can report on the basis of manhour & quantity and can show effiency on the basis of earned manhurs vs actual manhours and earned quantities.





Imran

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts