Assigning Resource to Hammock Activity?

F
Ferdinand U. 👤 Member for 18 years 10 months

try to change the BQ everytime u update, if hammocks UPT is 100, and the Orig Dur is changing, then u can get a new BQ everytime u update,then fix the UPT again.. set a milestone start or activity for hammock to be able to update it

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Sajid,

ya floating BQ dependant on the Duration.



Wish is a variable ,for me a fucntion of time.

My great grand father wished a Gramphone and that was the normal , my grand father wished a radio , my father a hi-fi system , my wish for the time being you know.

regards

deb

S
Sajid Balma 👤 Member for 19 years

Dear Deb

A floating BQ???????

Too much to ask/wish for, may be........



I don’t have any other ideas for now. May be someone else in the community shed some light on this Floating BQ.

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Sajid,

I dont want to put BQ because the duration of the project will vary and i want the BQ as well to vary accordingly.

kind regards

deb

S
Sajid Balma 👤 Member for 19 years

Hi Ravi

Why shouldn’t you just put BQ as your intended Units per Day x Duration of Hammock activity? P3 uses BQ to calculate BC & QTD etc rather Units/day to calculate BQ and BC etc.


Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts