Target Histogram

J
Jamie Welch 👤 Member for 19 years 1 month
J
Jamie Welch 👤 Member for 19 years 1 month

Thanks guys- done and working, must have been a glitsch somewhere as I made a new copy of the project and it worked.

A
A D 👤 Member for 19 years

Hi Jamie,



Go to Tools --> Graphic report --> Resource & Cost



Go to CONTENT tab and tick the TARGET1 box



U must have set target before doing this.



Select the resource / cost item, whatvere u want and say RUN.



It shud work for u



Cheers,



Ravi

J
John Lawson 👤 Member for 21 years 8 months

Hi Jamie,



Try exporting the data out of P3 via an Excel spreadsheet format, first for Target then for the current plan.



Then combine your data and produce your Target / Current chart on a user friendly graph.



Regards



John L.

A
Anoon Iimos 👤 Member for 19 years 8 months

make sure your Target Plan is resource loaded; update it that it has progressed perfectly as planned; and make your histogram

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts