Thanks guys- done and working, must have been a glitsch somewhere as I made a new copy of the project and it worked.
Hi Jamie,
Go to Tools --> Graphic report --> Resource & Cost
Go to CONTENT tab and tick the TARGET1 box
U must have set target before doing this.
Select the resource / cost item, whatvere u want and say RUN.
It shud work for u
Cheers,
Ravi
Hi Jamie,
Try exporting the data out of P3 via an Excel spreadsheet format, first for Target then for the current plan.
Then combine your data and produce your Target / Current chart on a user friendly graph.
Regards
John L.
no problem, if you want more, do not hesitate to hire me
Thanks Anoon all done as you suggested and no luck....
make sure your Target Plan is resource loaded; update it that it has progressed perfectly as planned; and make your histogram