Activity with Cost But Duration is Dependant in P3

J
John Raper 👤 Member for 22 years

Ben



Hammocks is the right way to go. You need a S-S from activity to hammock and F-F from hammock to activity. Keep the moving task as an activity and the dependent task as a hammock. Then as one changes the other changes with it.



Using just a F-F and keeping the dependent task as an activity will not adjust its duration, only its finish.