Activity with Cost But Duration is Dependant in P3
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Wonderful...thankyou.
Wonderful...thankyou.
Ben
Hammocks is the right way to go. You need a S-S from activity to hammock and F-F from hammock to activity. Keep the moving task as an activity and the dependent task as a hammock. Then as one changes the other changes with it.
Using just a F-F and keeping the dependent task as an activity will not adjust its duration, only its finish.