Thank you very much Johnny Kesserwany, Raviraj Bhedase and Tom Nug for giving the answers to my question.
Yes,
We also calculate percent complete of overal project:
%complete (actual)=BCWP/BAC
%complete (plan)=BCWS/BAC
Budget amount
Planned Value
Earned Value
Actual Value
There r three things:
Planned Value: Budgeted Cost of work Scheduled (BCWS)
Earned Value: Budgeted Cost of Work Performed (BCWP)
Actual Cost: Actual Cost of Work Performed (ACWP)
From these three values, u can hav SPI and CPI (Schedule Performance Index and Cost Performance Index)
SPI = EV / PV
CPI = EV / AC
For more details, apart from Paul Harris paper, u may also refer to PMBOK.
Cheers,
Rav
Go to the the technical paper of Mr. Paul Harris, youll have all what do you need and more...
http://www.eh.com.au/Technical%20Papers/020820%20EVPM%20Presentation%20…
JK