Front-loaded Project Baseline !

D
Deepak Jain 👤 Member for 20 years 4 months
K
Kamarul Bahrin Hassan 👤 Member for 20 years 9 months

Hi deepak.. yes but depending on your contract term. if your client giving a milestone payment is very good to do front loaded. you can earn in early stage. good for cash flow. if actual progress payment better no to do front loaded...


D
Deepak Jain 👤 Member for 20 years 4 months

Thnx Daniel..So In such projects, if cost projections are also front-loaded, then there will be a reasonable possibility of making payments for work not completed..Isn’t it ?



Cheers

Deepak

D
Daniel Limson 👤 Member for 24 years 8 months

It depends on what kind of project you have. There are projects which would require you to do the bulk of the work up front and so the ideal ’S’ curve in this case is not applicable.



Cheers Mate,

Daniel

D
Deepak Jain 👤 Member for 20 years 4 months

Oki..if it makes a difference, then I don’t think that we could ever be able to achieve a "S" curve while plotting Budget value against Time. So the moral is :) that Project Baseline’s should never be front loaded. What you think ?

K
Kamarul Bahrin Hassan 👤 Member for 20 years 9 months

hi... yes its make a difference. if you distribute resource/cost value. the percentage of the value is depending on duration you put in. all the cost will culculate automaticly or prorate by the duration you assign. if we make front loaded. we can earn early. (cash flow forecast/budget). for finacialy maonitoring.

K
Karen Smith 👤 Member for 19 years

Hi Jain,

Forward pass is Early Start plus Duration = Early Finish, at points of convergence, the latest early finish pervails. Early Finish of last activity = late finish of network.

Backward Pass is Late Finish minus Duration = Late Start, at points of convergence the earliest late start is used.



I don’y think it makes a difference in the way you distribute Resource/Cost values.



Cheers.

Karen

D
Deepak Jain 👤 Member for 20 years 4 months

Thnx Tq..extending onto this, does both kinds of Baseline’s make a difference in the way you distribute Resources/Cost values into your schedule ?

K
Kamarul Bahrin Hassan 👤 Member for 20 years 9 months

Hi Deepak..



Front Loaded - you derive all the activity in early start.. etc. 1 year project. you assign all the activity start concurrent. let say you have 100 activity. 80 activity almost completed 6 month before completed project. so we call this fornt loaded.



tq

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts