duration calculation in p3& p5

J
John Raper 👤 Member for 22 years

Mangesh



This is only a guess but check it out.

I assume your ’planning unit’ in P3 is ’Days’. In P5 the planning unit is always hours, but appears as days. You will need to check the hours/day in ’Admin|Admin Preferences|Time Periods’. This deterimnes the calculation for hours per day etc.

You may need to change the duration, then change it back, for the duration to be re-calculated.



Hope this helps.