Thnx Deepak...I agree with you on requirement of 9 Men days but in the current situation , its the same resource & thus 3 men can work every day for 3 days to equate to 9 Men Days in total. So, I need 3 men to complete the activity NOT 9 as defined by P3
Thnx Raviraj...but i dont think that its an issue related to Report Writing/ID etc. The problem I could imagine is because in P3 , Budgeted Quantity (BQ) = (Units/Day x Activity Duration) . This linear equation doesnt incorporate any variable for Concurrent/Repetitive units
VERY Interesting....
Shud not happen actually.
As Datta has said, u must hav used single resource.
Better way wud b, go to TOOLS --> GRAPHIC REPORTS --> RESOURCE AND COST
Add one more ID into it
and then produce the Histogram / Curve required.
Remember to change items in following tabs at least:
Resource Selection
Content
Date
Selection
If there is still problem, plz revert back.
Cheers,
Raviraj
Dear Deepak,
If the trades are different, then use different resources.
If they are doing same work, use a same resource (Welder etc)
You require 9 mandays to do the work, with 3 no of resources, you will take 3 days.
Unless you have a different plan for these people thruout the rest of the project, you can always combine the resources. & also think about the type of reports u want to generate & then decide.
Cheers
Deepak
Dear Deepak,
If the trades are different, then use different resources.
If they are doing same work, use a same resource (Welder etc)
You require 9 mandays to do the work, with 3 no of resources, you will take 3 days.
Unless you have a different plan for these people thruout the rest of the project, you can always combine the resources. & also think about the type of reports u want to generate & then decide.
Cheers
Deepak