Bar Chart & Network (PERT) Finish Dates not Matchi

L
Luca Basile 👤 Member for 22 years 11 months

I just try it on my P3 and there are not any discrepancy between the bar chart and the pert data.

As are extrimated once for ever, or until next scheduling.

I used a 7 working days calendar.



Try to see which info are you asking to be shown in pert view.



If You want a copy of this and see how is running on your P3 send me You email.

A
Amr Tabbarah 👤 Member for 22 years 5 months

To clarify my point, herebelow is a simple example.



Create a new project with planning unit in weeks, starting on mondays and with a start date of January 5th 2004.



Activity 1 has duration of 2 weeks and is linked with FS to Activity 2 that has a duration of 3 weeks.



The Bar Chart Layout shows Activity 1 finishing on January 18th 2004, and Activity 2 on February 8th, 2004, and both are correct.



Now, if you go to View, PERT, it shows Activity 1 finishing on January 12th 2004, and Activity 2 on February 2nd, 2004, and both are wrong. These 2 finish dates represent the starting dates of the weeks in which these activities end.



Hope my example is clear.



Anybody has an idea what is happening?



Thanks.


M
MK TSE 👤 Member for 24 years 3 months

please check the start day of the week are same. Project property and report option.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts