How to change the Activity ID of a group of activities?

D
Daniel Limson 👤 Member for 24 years 8 months

There is another way of doing it by copy and paste. Select auto increment and delete the ones you want to change. The only problem here is you will loose the relationship outside of the group you copied and pasted.



Cheers

Daniel

F
Ferdinand U. 👤 Member for 18 years 10 months

example change A100000000 to B200000000



global change



if ACT CN A1

then ACT EQ B2 & right(ACT,8)



run

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Ferdinand and Dattatreya ,

can you please list in more details the procedure.

regards

deb

D
DATTATREYA PADHARTHI 👤 Member for 23 years 1 month

Pranab,



Use the Global Change; if you want to change a charecter/s in the middle, extract all charecters before that lot and also extract all charecters after that lot and save as a temporary variable. then use the concatenate function.

Cheers

Dattatreya

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Ferdinand,

Thanks for your reply can please elaborate how to use this function.

regards

deb

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts