P5 Project group export issues to P3

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Kevin



You can copy a project group as a project into another project group. It will be possible to export the three P5-Projects to P3. You’ll have 3 project groups. Then copy those P3-projects into a fourth (new) Project. To this for the complete life of your projects will be a horror.

It is a break of structures. In any case you’ll loose informations.

Maybe another solution will help: I suppose, planners in construction area want to keep their old P3 and reporting has to be done in P5. In such cases -if it’s not possible to convince old planners that a common solution is better, I let them schedule in P3, import with "update" into P5 and do the reporting. Import then only will be one-way and with reliable results.

Regards

Dieter

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts