Duration with decimal point...

R
Rick Aquino 👤 Member for 21 years 2 months
G
Gary Moffatt 👤 Member for 23 years 7 months

Hi Rick,

The calculation in P3 works in whole units - your only option for parts of a day is hours, but you can run a secondary schedule, for example a steel erection schedule, and import or key in a summary level into your main schedule. Even if your client demands it as backup it will only detail one part of your work.

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Rick



No you can’t! I agree to Raviraj, without decimals should be ok for longer projects. In P3e it would be poosible but there too I didn’t use it - for longer projects.



Dieter

R
Rick Aquino 👤 Member for 21 years 2 months

Hi Rav and Anoon,



Thanks for your immediate response, but is there a possibility that i could set up my duration with a decimal point? like 2.3 days, 2.4 days, etc, etc. because when i enter the duration with decimal point the primavera will round it off to a whole number, and when you organized it to see the schedule duration it is less of what i have planned.is there a possibility for p3 to accept whatever duration i encoded.

Thanks Again.

A
A D 👤 Member for 19 years

Hi Rick,



If the project is long, why u want to put duration in hours. Do u want to be so transparent with ur client that u will activity worth in hours only.



Even, it is neither required by Client/Consultant nor by project team.



Hours are used in mostly maintenance projects, where shutdown means loosing money.



Its of no point in putting duartion in hours for a long project



Cheers,



Raviraj

A
Anoon Iimos 👤 Member for 19 years 8 months

i suggest that you should never do that, if it’s day or hour so be it!

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts