How to link schedules?

G
Gün Göksu 👤 Member for 21 years 2 months

hello,



"Interproject Relationships" is what you are looking for.



password: INTRPROJ



it is located under:



P3PROGS\INTRPROJ.EXE



please read the related help files BEFORE doing any changes.

Always write the changes down, link between milestones clearly defined as "linked/from". If you don’t do this, after some time, you will forget they are there and wonder (possibly spending hours in the process) why the schedule is acting weird.



hope this helps.



Gün :)

G
Ghassan Zihri 👤 Member for 20 years 1 month

Hi,



thank you for your reply. I want to create a hammock activity in one program then to link this activity to an external program. My purpose is to reduce the number of activities of the program that I submit to the Engineer Representative. "Interproject" offers the option to link 2 programs with a FS link. I will keep trying and let you know.



Regards,

K
Karen Smith 👤 Member for 19 years

Hi Ghassan,

Do you mean reduce the number of activities by linking to your other schedules and thus reducing repetition?

If so can your other schedules be sub-projects and then link with milestones, I haven’t used/considered a hammock but the milestones work well.

Cheers.

Karen

B
Brennan Westworth 👤 Member for 23 years 3 months

If they are sub-projects of the same project group this isnt a problem.



I have never tried to use interproj for hammocks, but i imagine it wouldnt work.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts