How to link schedules?
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
hello,
"Interproject Relationships" is what you are looking for.
password: INTRPROJ
it is located under:
P3PROGS\INTRPROJ.EXE
please read the related help files BEFORE doing any changes.
Always write the changes down, link between milestones clearly defined as "linked/from". If you don’t do this, after some time, you will forget they are there and wonder (possibly spending hours in the process) why the schedule is acting weird.
hope this helps.
Gün :)
Hi,
thank you for your reply. I want to create a hammock activity in one program then to link this activity to an external program. My purpose is to reduce the number of activities of the program that I submit to the Engineer Representative. "Interproject" offers the option to link 2 programs with a FS link. I will keep trying and let you know.
Regards,
Hi Ghassan,
Do you mean reduce the number of activities by linking to your other schedules and thus reducing repetition?
If so can your other schedules be sub-projects and then link with milestones, I havent used/considered a hammock but the milestones work well.
Cheers.
Karen
If they are sub-projects of the same project group this isnt a problem.
I have never tried to use interproj for hammocks, but i imagine it wouldnt work.