Marked boxes on PERT View

N
Nicolas Berger 👤 Member for 20 years

I know it’s strange but this is the way I received the schedule...

Anyhow, those activities have constraints...

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

How can there be % complete without start, anyway I hope you have now fixed the problem.



Regards,



Ashraf

N
Nicolas Berger 👤 Member for 20 years

Actually, there is no start date but there is % complete greater than "0".



Thanks anyway...

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

Check Again,



Single diagonal line is for started activites. You must have put Actual start date for these.



Regards,





Ashraf

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

Nicolas,



By striped if you mean X crossed , then it is the completed activites.



Regards,



Ashraf

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts