updating an activity out of logic
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Thnx you very much i get your answer...
No, you do not need to modify your target plan; the target plan is basically for comparison with your running/current plan so dont modify it. So just modify only the updating/current schedule.
However, you can decide to create another target with this new plan. Recall that P3 allows you to create as many target projects as you want, though, you can compare only two targets to the current schedule at any one time.
I hope this helps.
Regards
Akin
Nigeria
thanks my friend, but what about target plan should i also modify the link or just in i modify in updating program only.
thnx again
Update as you would update any other activity: Actual start date, percentage complete, remaining duration, resource usage etc. However, remember to check the effect of this out of sequence activity on its predecessors/successor; you may have to break and modify the link and introduce some lag. Generally it will not impact on the other activities if the above precautions are taken into consideration.
Regards,
Akin
Nigeria