Sheduling - Loop

H
Hannes de Bruyne 👤 Member for 20 years 10 months

Hello Jaya



Don’t use F9 for scheduling, use the Icon with the red clock.



This will give you the report



Hannes

J
J Venkatesh PMP PSP ACIArb 👤 Member for 19 years 10 months

Dear Ramana,



thanks for ur immediate response...



but when am scheduling it, am not getting detailed report, just its showing scheduling terminated and loops detected...



I don kno, whther any installation file wud be missing????

V
VENKAT RAMANA 👤 Member for 19 years 4 months

Heyy...



After scheduling i think you got a report of the loops detected...Actually loops are traced when activities are linked incorrect..i.e example of a loop is A-B-C-D-A..just go to the activity A and check its predecessor or successor and make correction..ur schedule shall be successful.



Regards,

VENKAT RAMANA

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts