Scheduling P3 and the activities stay where they are?!
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
if not mistaken.. there is an option to "apply" the datadate from the master to all the subs, when u schedle from the master.
can someone confirm?
long time didnt use subproj....
Ive been a bit dim, weve got sub projects and I thought that by scheduling the overall project it would move the data dates for all the subs...
Having now scheduled the subs all is happy!
check activies with constraints
Thanks for your responses chaps, tried and checked both but sadly no fix!
Weve sent a prx to Primavera so well see what they come back with...
possibly you are NOT viewing current bar (ES/EF)
but viewing baseline (T1ES/T1EF)?
It’s strange but one possible reason is the option that you choose to apply when scheduling activities.
Check this: instead of pressing F9 go to Tools --->> Schedule --->> Options. Select the General tab under "When scheduling activities apply" select Progress Override. Then schedule.
If you select Retained Logic it could create the kind of scenario that you presented.
When you choose Progress Override, P3 ignores the relationship (logic) and allow the activity to be rescheduled.
Please just check it out and let me have your feedback.
Akin Adurosakin
Nigeria