Project / Activity Dates

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you don't really specify a new start date for each activity that what the logic and durations are for. Progress the activities accordingly with actual start and or finish dates and change the remaining duration if the activity is in progress and not complete. Then move the data date and re-schedule the project.

S
Syam Mohan 👤 Member for 10 years 2 months

Hi everyone,

                  In my p6 software dates are not changing for particular activities according to the relation given. The calender assigned is same for all activities. Please help me with your valuable suggestions to fix this.

J
Jonathan Ward 👤 Member for 19 years 4 months

sorry Steven,

i’m getting an error the reads - Invalid Criteria Code



i have nothing other than SNE in that row now

under that row i have this:

MS EQ ES - 20

S
Steven Oliver 👤 Member for 23 years 7 months

Nothing, all it is doing is removing any existing constraints, as in P3 an activity can only be assigned one type of constraint.

J
Jonathan Ward 👤 Member for 19 years 4 months

what do i need to enter in the Data Item/Value column on the same row as SNE?

i.e

then SNE EQ ___

S
Steven Oliver 👤 Member for 23 years 7 months

If you are trying to overrule the logic of your schedule, you will need to use Mandatory Constraints.



On the change tab of Global change



If Act Cn "SYS"



Then SNE = ’ Removes any existing constraints

MS = ES - 20





Then re-schedule


S
Steven Oliver 👤 Member for 23 years 7 months

To try and phrase your question into english, is it



If

Activity ID Contains "SYS"

Then

Constrain the start to 20 days prior to the current early start ?

J
Jonathan Ward 👤 Member for 19 years 4 months

this will be the very last question on this subject:

when i apply the Global change (i have made several copies of my Plan so i’ve got back-up), do i enter the criteria on the Change of the Selection tab? i assume it is the Change tab, when i have runu this i get the error that the activities already exist??

the criteria i enter are as follows:



IF : ACT | CN | SYS (my activity codes i want to change) | - | 20d.



THEN: ACT | CN | ACT





thanks again

J
Jonathan Ward 👤 Member for 19 years 4 months

how do you specify a new start date for activities in a global change? sorry to keep asking these tedious questions

S
Steven Oliver 👤 Member for 23 years 7 months

You could use a combination of activity codes and global change, if you have a lot of changes, but a well constructed schedule is by far the best option.

J
Jonathan Ward 👤 Member for 19 years 4 months

,, so would i have to change the constrains on each individual activity or is there a method of group change? obviously alot of the activitis start at later dates in the schedule, i have many activities running in different calendars so if changing the constrains is the best method i woould rather use this,,

thank you very much for your help

S
Steven Oliver 👤 Member for 23 years 7 months

Thats because the activities placement in time is dictated by the logic in the schedule. If you need to impose a different start/finish, then use constraints or calendars

J
Jonathan Ward 👤 Member for 19 years 4 months

, sorry, one more, that works when the scheduled data date is taken forward, what about when the scheduled data date is taken back? the line moves but the activity dates stay where they are?

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts