Hi all,



i have made a mistake in the data date entry and now the result is correct.



After entrering all my progress till date, how an i get the progress cure i.e. s-curve?



vasudevan

M
Mark Chapman 👤 Member for 20 years

Vasudevan,



Go to File and Project Overview and you should see the project start date and the data date. Hopefully you now know the difference between them.



mark

C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Vesuduram,



I think your link for each activity is not proper.



Please check and let me know.



Cheers,



Charlie

B
Bijaya Bajracharya 👤 Member for 21 years 3 months

Further to earlier discussion on Data date:



If all its predecessors are completed, the earliest date an activity can start is on the data date.



So it appears your data date is even earlier than the Actual start date of your activity 1. Instead of F9, if you had pressed the schedule button, P3 will generate a schedule report which will show you (in P3.out file) what irregularaties were there in your programme information.

B
Bijaya Bajracharya 👤 Member for 21 years 3 months

Data date is the last date progress was recorded in terms of actual dates, % complete, remaining durations, and/or actual quantities and costs.



Start date- which one? Early Start date is when an activity can start earliest. Late Start Date- the latest date when an activity can start without delaying the project. Actual start date - when the activity actually started.

S
Santhosh kumar Narayanan 👤 Member for 19 years 10 months

ur relation is FS right? in ur case the predecessor is finished so the sucessor will come come to date date even before the finish date of ur predecessor i think u made mistake of not shited the data date cheak the data date !!! ( must be actual finish date or the date of actual entry)

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Vasudevan,



I suppose, the data date of your project is earlier than the Actual Start of this activity. The activity is finished, so it ignored by scheduling. As the activity does no longer exist, it’s relationships are ignored as well.



Regards



Dieter

V
vasudevan Dhakshinamoorthy 👤 Member for 19 years 2 months

i put actual start and actual finish bu a tick and also i put 10 daya lag in FS relationship.



Still i am getting the same result

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

did u tick actual start and actual finish( if the activity started and ended as planned ) or u put actual start and then put 100 % complted , and as mr. rodel noted did u put a 10 days lag on a FS relationship

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts