How P3 is calculating % complete.....
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
hi ronald how are you nice to hear from you.......
i have done that already what all of you have mentioned
i even ask some planners here also.....
let me rephrase my question......
if i will summarize all the activities the % complete lets say 67% complete
if i would schedule the programme it will show 57% why there is a difference.......i keep on encountering this problem
do i have to ask my boss to renew the license??? do i have to replace my PC??? :)
follow up question......
lets say i have a delay of 8% on the over all programme i would like to know what % of the overall delays is the blockworks alone????
tnx in advance guys :)
Hi Ray,
P3 calculates % complete by calculating the percentage of actual duration wrt Total duration. i.e (OD-RD)/OD
However, if you dont want to use this rule, you can remove the linkage by Autocost rule, But in that case you have to feed % completion and Remaining Duration manually.
Yes, we can set % completion for summerized activity (Tool >Option>summerization)in three way i.e. by Duration, Resources unit and cost.
and even you can set different method for different section if you are using more than one calander in your project.
Thanks
Prabin Kumar
Dear Rey,
How you doing?
Try to check AutoCost Rule. You can click whichever fit to your requirements in calculation.
Regards,
Ronald
When do summary, summarized PCT=
[(SumOfOD - SumOfRD)/SumOfOD]x100%
According to P3 manual, PCT is "The proportion of an activity that has been completed".
PCT=[(OD-RD)/OD]x100%