In my opinion , you should add a resources called ’weight value’ to your project. The BQ for any perticular activity will be same as ( or multiple of any constant like 100, 1000,.. etc as per your convenience ), what weight value you want to assigned that perticulat activity.

Make sure that all the required link is marked in ’Auto cost rule’, so that p3 will calculate the ’actual to date’ & ’actual this period’ as per OD & RD.



As, Mr Karim said, it will be updated automatically in regards of ’Actual to date’, ’To complete’....etc after each updates, and u can produce your reports in terms of desired weight value.



thanks,



Prabin Kumar

K
Karim Mounir 👤 Member for 20 years 2 months

You can make a dummy resource (for example called "activity days"), then assign all of your activities with this resource.



The BQ of this resource will be equal to the OD of each activity.



After that when u update your schedule, the actual units will be updated automatically which will give u the overall actual progress % (u can generate a tabular report for this).

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts